§ 22-204. Location of certain utility structures.  


Latest version.
  • (a)

    No construction or installation of the following named utility structures shall commence without the Planning Commission and the City Council having first approved the location of the structure:

    (1)

    Electric substations;

    (2)

    Electric switching stations;

    (3)

    Natural gas line terminals, pressure reducing stations, regulating, odorizing, or metering stations;

    (4)

    Telephone exchange buildings.

    (b)

    Prior to the issuance of a building permit and at the time of approval of the location, a plot plan shall be submitted showing:

    (1)

    The outline of the structure;

    (2)

    The height thereof;

    (3)

    The type of construction;

    (4)

    The set-back of the structure from property lines; and

    (5)

    The nature and character of the surrounding property.

    (c)

    Prior to the issuance of a building permit, and as a condition thereof, the screening of such structures with those materials which will cause the installation to blend most favorably with the surrounding property shall be required.

(Ord. Nos. 0-1833; 0-1854)